Client
|
Description of Project
|
Scope of Work
|
Period
|
|
Gas Malaysia
|
LPCC of NGDS Meru (Top Groove)
- Pipeline
|
Manpower supply, pipeline installation, NDT
|
March 2005
COMPLETED
|
|
Gas Malaysia
|
LPCC of NGDS – Kapar (Southern Acid)
- Pipeline
|
Manpower supply, pipeline installation, NDT
|
March 2005
COMPLETED
|
|
Gas Malaysia
|
LPCC of NGDS – Kapar (Incaplas)
- Pipeline
|
Manpower supply, pipeline installation, NDT
|
March 2005
COMPLETED
|
|
Gas Malaysia
|
LPCC of NGDS – Shah Alam
|
Manpower supply, pipeline installation, NDT
|
April 2005
COMPLETED
|
|
Petronas (SBO)
|
Riser Guard
Boat Landing
- Carry out repair and maintenance
|
Fabrication and installation
|
May 2006
COMPLETED
|
|
PBJV Group SB
|
Small Project:-
Fabrication of Davit/Semarang Field/Kikih Pipelines
|
Manpower supply, fabrication works
|
Jul – Dec 07
COMPLETED
|
|
PBJV Group SB
|
SBO & SKO Underwater Maintenance
|
Manpower supply
|
Jul – Oct 07
COMPLETED
|
|
PBJV Group SB
|
West Lutong Pipeline Replacement
|
Manpower supply, pipeline installation
|
2007 – 2008
COMPLETED
|
|
PBJV Group SB
|
Labuan Gas pipeline replacement project
-
Supply of manpower to carry out installation of pipelines, and
-
Fabricated Davit for LGAST.
|
Manpower supply
|
Jul 07 – Jan 08
COMPLETED
|
|
PBJV Group SB
|
Shore approach, installation of pipeline at Kikeh
|
Manpower supply
|
Nov 07 – Jan 08
COMPLETED
|
|
PBJV Group SB
|
Kepong-Tiong Sectional Pipeline Replacement
|
Manpower supply
|
Mar – Nov 08
COMPLETED
|
|
Alam Maritim SB
|
Rig Up & Derig Up work on Lewek Launcher Barge
|
The provision of manpower supply, engineering solution, equipment, machineries, materials and consumables, installation commissioning and maintenance
|
Oct 2008
COMPLETED
|
|
Alam Maritim SB
|
Cleaning, tie down bracing and installation of wing port at Lewek Launcher Barge
|
The provision of manpower supply, engineering solution, equipment, machineries, materials and consumables, installation commissioning and maintenance
|
Nov 08
COMPLETED
|
|
Alam Maritim SB
|
Manpower supply on Lewek Launcher Barge
|
Manpower supply
|
Nov 08
COMPLETED
|
|
PBJV Group
|
Manpower supply and equipment for Baram Pipeline Replacement project
|
Manpower supply
|
June 09
COMPLETED
|
|
TL Offshore/Newsea Works
|
Rig up work/modification of skid beam onboard of Saipem S45
|
The provision of manpower supply, engineering solution, equipment, machineries, materials and consumables, installation commissioning and maintenance
|
Aug 09
COMPLETED
|
|
TL Offshore/Newsea Works
|
Rig down and cleaning work onboard of Saipem S45
|
The provision of manpower supply, engineering solution, equipment, machineries, materials and consumables, installation commissioning and maintenance
|
Oct 09
COMPLETED
|